North County Blvd Phase 1 update

North County Blvd. - Phase I (SR-92 to Provo Reservoir Canal) - Construction Update

Traffic Impacts:

* NEW - Crews will be working along Panorama Drive either this afternoon or on Monday, September 20. Please expect atemporary road closure at this location. 

- The speed limit will remain at 35 mph, but please proceed with added caution in the construction zone, as fines will double for speeding.


Construction Activities:

- Home demolition along the corridor will be ongoing the remainder of this week (through September 18).


Pedestrian and Student Safety:

 - Work will be ongoing through November in front of Lone Peak High School. Student pedestrians are encouraged to walk on the east side of North County Blvd (4800 West) at this time. 

 - Please proceed with caution while walking along North County Blvd. and do not walk through the construction zone or outside of designated crosswalks. Please be aware that crews are using large machinery and equipment, making it more difficult to see pedestrians. Use alternate routes as directed and avoid walking along the roadway when possible. 

- Be alert and attentive to your surroundings and only cross North County Blvd. at signalized intersections and designatedpedestrian crossings



Hours of Operation: 7:00 a.m. to 5:30 p.m.
Work Days: Construction activities will be ongoing Monday-Saturday/6 days per week


***The scheduled activities are subject to change due to weather related issues***

Please contact a project representative at 801.319.2603 or northcountyblvd@horrocks.com with any questions or concerns.

Sincerely,

Kimberlee Winterton
North County Boulevard Project Team
Project Hotline: 801.319.2603
Project E-mail: northcountyblvd@horrocks.com

Tuesday, September 21, 2010

PTSA Membership Drive

September is our PTSA membership drive!  If you would like to sign up the cost is $8.00 each and you can do this in the finance office.  We will be doing a drawing for an Ogio bag and we are participating in a contest with Lehi, AF and PGHS and Chick-fil-a.  The high school with the most PTSA members will receive lunch for their school sponsored by Chick-fil-a. 
GO KNIGHTS!

Wednesday, September 8, 2010

North County Blvd Phase I update

North County Blvd. - Phase I (SR-92 to Provo Reservoir Canal) - Construction Update

Traffic Impacts:

* NEW - Please expect flagging operations and potential delays at Knight Avenue during the latter part of next week (Sept. 8-11) and on Monday, September 13. Flagging operations will be used to accommodate construction activities along the roadway.

- The speed limit will remain at 35 mph, but please proceed with added caution in the construction zone, as fines will double for speeding.


Construction Activities:

- Home demolition along the corridor will be ongoing the week of September 6th.


Pedestrian and Student Safety:

 - Work will be ongoing through November in front of Lone Peak High School.  Student pedestrians are encouraged to walk on the east side of North County Blvd (4800 West) at this time. 

 - Please proceed with caution while walking along North County Blvd. and do not walk through the construction zone. Please be aware that crews are using large machinery and equipment, making it more difficult to see pedestrians. Use alternate routes as directed and avoid walking along the roadway when possible. 

- Be alert and attentive to your surroundings and only cross North County Blvd. at signalized intersections and designatedpedestrian crossings



Hours of Operation: 7:00 a.m. to 5:30 p.m.
Work Days: Construction activities will be ongoing Monday-Saturday/6 days per week


***The scheduled activities are subject to change due to weather related issues***

Please contact a project representative at 801.319.2603 or northcountyblvd@horrocks.com with any questions or concerns.

Sincerely,

Kimberlee Winterton
North County Boulevard Project Team
Project Hotline: 801.319.2603
Project E-mail: northcountyblvd@horrocks.com

Thursday, August 26, 2010

2010-2011 PTSA Budget

LONE PEAK PTSA BUDGET
2010-2011
INCOME/net worth:

Balance Forward...................................................................4,663.42    
Membership Dues (local portion only)…………………….5,000.00

TOTAL INCOME………………………………………………… 9,663.42
EXPENSES:
Executive Expenses………………………………………….475.00 Overhead
PTA convention
Volunteer appreciation

Community Involvement………………………………….1,000.00
Teacher Appreciation
Teacher Dinners

Individual Development…………………………………… 850.00
Reflections
Student Recognition

Legislative………………………………………………….. 50.00    
Legislative Convention, PTA Day

Membership………………………………………………….50.00

Grants/Scholarships………………………………………..5,300.00          
 
Miscellaneous……………………………………………… 300.00  

Carry Over for Next Year………………………………….1,638.40

Total Expenses……………………………………………………………9,663.42


Questions…Call Diane Lohner, Lone Peak PTSA Treasurer 
801-763-9576

Next PTSA Meeting - Wed. Sept 15th at 10a

We would like your input!! Please join us at our next PTSA - Wed. Sept. 15th in the Conference room at 10a.

Be the Change Day - Sept. 8th, 9th and 10th

This year's "Be the Change" Day will be Sept. 8th,  9th and 10th. If you're interested in volunteering or would like your student to participate. Please contact PTSA.

Picture Day - Sept. 2nd and 3rd

Picture Day is NEXT week - Sept. 2nd and 3rd and we are still in need of volunteers. Please contact PTSA if you're available to help.